  1. Current release
  2. Completed Releases
    1. Release v0.10 Schedule
    2. Release v0.9 Schedule

Current release

The current release schedule is posted on the RAPIDS Maintainers Docs page.

Completed Releases

Historical list of completed releases

Release v0.10 Schedule

Phase Start End Duration
New Development Wed, Aug 14th Wed, Sep 25th 30 days
Burn Down Thu, Sep 26th Wed, Oct 2nd 5 days
Code Freeze/Testing Thu, Oct 10th Wed, Oct 16th 5 days
Release Thu, Oct 17th Thu, Oct 17th 1 day

Release v0.9 Schedule

Phase Start End Duration
New Development Mon, Jun 24th Tue, Aug 6th 30 days
Burn Down Wed, Aug 7th Tue, Aug 13th 5 days
Code Freeze/Testing Wed, Aug 14th Tue, Aug 20th 5 days
Release Wed, Aug 21st Wed, Aug 21st 1 day