RAPIDS Maintainers Docs
RAPIDS projects use an established set of guidelines and procedures for all projects. These are available for the community to review and provide feedback on.
Intended audience
Developers
Project Leads
Operations
Release v25.02 Schedule
NOTE: Dates are subject to change at anytime. Completed release schedules are posted here.
Phase | Start | End | Duration |
---|---|---|---|
Development (cuDF/RMM/rapids-cmake/cugraph-ops/raft/dask-cuda/ucx-py) | Thu, Nov 14, 2024 | Wed, Jan 22, 2025 | 43 days |
Development (others) | Thu, Nov 21, 2024 | Wed, Jan 29, 2025 | 43 days |
Burn Down(cuDF/RMM/rapids-cmake/cugraph-ops/raft/dask-cuda/ucx-py) | Thu, Jan 23, 2025 | Wed, Jan 29, 2025 | 5 days |
Burn Down (others) | Thu, Jan 30, 2025 | Wed, Feb 5, 2025 | 5 days |
Code Freeze/Testing (cuDF/RMM/rapids-cmake/cugraph-ops/raft/dask-cuda/ucx-py) 1 | Thu, Jan 30, 2025 | Tue, Feb 11, 2025 | 9 days |
Code Freeze/Testing (others) | Thu, Feb 6, 2025 | Tue, Feb 11, 2025 | 4 days |
Release | Wed, Feb 12, 2025 | Thu, Feb 13, 2025 | 2 days |
PROPOSED Release v25.04 Schedule
Phase | Start | End | Duration |
---|---|---|---|
Development (cuDF/RMM/rapids-cmake/cugraph-ops/raft/dask-cuda/ucx-py) | Thu, Jan 23, 2025 | Wed, Mar 12, 2025 | 34 days |
Development (others) | Thu, Jan 30, 2025 | Wed, Mar 19, 2025 | 34 days |
Burn Down(cuDF/RMM/rapids-cmake/cugraph-ops/raft/dask-cuda/ucx-py) | Thu, Mar 13, 2025 | Wed, Mar 19, 2025 | 5 days |
Burn Down (others) | Thu, Mar 20, 2025 | Wed, Apr 2, 2025 | 8 days |
Code Freeze/Testing (cuDF/RMM/rapids-cmake/cugraph-ops/raft/dask-cuda/ucx-py) 1 | Thu, Mar 20, 2025 | Tue, Apr 8, 2025 | 12 days |
Code Freeze/Testing (others) | Thu, Apr 3, 2025 | Tue, Apr 8, 2025 | 4 days |
Release | Wed, Apr 9, 2025 | Thu, Apr 10, 2025 | 2 days |